⚡ OSHA Elec Practice Test

DMV Practice Test Hub › OSHA Elec › Practice test 18

OSHA Elec practice test 18

25 multiple-choice questions for the OSHA Electrical Safety (Subpart S) Practice Test. Pick an answer to see the rule behind it, quoted from the official source.

1. A worker needs to inspect the back of a dead-front switchboard assembly. Under which condition is working space NOT required behind this equipment?

2. An electrician is installing a new junction box on a concrete wall at a construction jobsite. According to the mounting requirements for electric equipment, which method is prohibited for securing the box?

3. An electrician is wiring a receptacle and needs to connect the grounding contact. To what must the grounding contact be connected?

4. An electrician is working on deenergized equipment that contains stored non-electrical energy capable of reenergizing the circuit parts. What action is required to ensure safety?

5. For systems over 600 volts nominal, where are open runs of non-metallic-sheathed cable or bare conductors permitted to be installed?

6. An electrician is installing a disconnecting means for an arc welder that does not have an integral disconnect. What is the minimum rating requirement for the switch or circuit breaker used as the disconnecting means?

7. An electrician is installing a sign at the service entrance equipment for an emergency power system. Under which condition is this sign NOT required?

8. A technician is maintaining a portable high-voltage system where the equipment grounding conductor continuity is continuously monitored. What automatic action must occur if the continuity of this grounding conductor is lost?

9. An electrician is protecting a feeder circuit over 600 volts using fuses. What is the maximum continuous ampere rating allowed for the fuse relative to the ampacity of the conductors it protects?

10. A worker is installing a ventilation unit for electrical equipment that relies on natural air circulation for cooling. To comply with safety requirements, how must the unit be positioned relative to walls and other equipment?

11. An industrial worker is inspecting a junction box and finds an unused opening. What is the required action to comply with the mechanical execution of work standards?

12. When an electrician installs a wireway to house and protect electric wires and cable, what is the required sequence for installing the conductors?

13. Before an electrician begins work on deenergized equipment, what action must be taken regarding stored electric energy if it might endanger personnel?

14. When an employer selects electrical equipment for a jobsite, what is the primary basis for determining that the equipment is safe for use?

15. Low-voltage switches (600 volts, nominal, or less) are installed in a room that also contains exposed live parts operating at over 600 volts. What is required to separate the low-voltage equipment from the high-voltage space?

16. An electrician is connecting a grounded conductor to a terminal. Which practice is prohibited to ensure safety and code compliance?

17. An electrician is installing threaded conduit in a Class I, Zone 1 hazardous location. To ensure the explosionproof integrity of the system and prevent sparking during a fault, what specific threading standard and tightness must be used?

18. An industrial worker is assessing whether a specific electrical panel is 'accessible' as applied to equipment. Which condition correctly describes an accessible piece of equipment?

19. An industrial electrician is installing custom-made electrical equipment designed specifically for a single customer. To ensure the installation is considered 'acceptable' under OSHA Subpart S without a nationally recognized testing laboratory listing, what must the electrician rely on?

20. An industrial worker is evaluating a new piece of electrical equipment for safety compliance. Which service is a 'Qualified testing laboratory' authorized to provide regarding product labels?

21. An electrician is installing an aerial communications circuit that runs partly outside a block. According to OSHA standards, what specific device must be provided on this circuit?

22. An electrician is installing equipment in a Class I, Zone 2 location containing a specific flammable gas. They have a piece of equipment listed for a Zone 1 location of the same gas. According to OSHA rules, what is the correct action?

23. An electrician is installing a DC circuit for fixed equipment that requires grounding. Unlike AC circuits, which specific allowance does OSHA provide for the routing of the equipment grounding conductor?

24. An electrician is selecting a two-pole circuit breaker to protect a 3-phase, corner-grounded delta circuit. Under what condition is this specific breaker type permitted for this application?

25. An electrician is selecting a cable type for a factory assembly where one or more conductors are insulated with highly compressed refractory mineral insulation and enclosed in a liquidtight and gastight continuous copper or alloy steel sheath. Which cable type matches this description?

← Test 17 · All tests · Test 19 →